5719 Project
Track the progress of our Sun Room Addition
Saturday, August 28, 2010
Dry Wall is going in
Dry wall is up and the prep for stucco is finished.
The stucco will be applied on Saturday and the final taping and dry wall finish will be done on Monday
Floors and cabinetry will be next.
Sunday, August 22, 2010
Final Sprinkler Heads
Here are the final sprinkler heads - Once we paint the pipe a matching brown color, the sprinklers will not be very noticeable.
Insulation inspection on Monday (8/23) and drywall starts on Tuesday!!!
Wednesday, August 18, 2010
Finally - Sprinklers Approved!
After a 6 week delay, the Fire Marshall approved the sprinkler design. They installed the sprinklers on Tuesday. The heads that are shown are only temporary, until they finish the "bucket test". Then, much smaller brass heads will be installed.