Saturday, August 28, 2010

Dry Wall is going in

Dry wall is up and the prep for stucco is finished.

The stucco will be applied on Saturday and the final taping and dry wall finish will be done on Monday

Floors and cabinetry will be next.


Posted by Picasa

Sunday, August 22, 2010

Final Sprinkler Heads

Here are the final sprinkler heads - Once we paint the pipe a matching brown color, the sprinklers will not be very noticeable.

Insulation inspection on Monday (8/23) and drywall starts on Tuesday!!!

Posted by Picasa

Wednesday, August 18, 2010

Finally - Sprinklers Approved!

After a 6 week delay, the Fire Marshall approved the sprinkler design. They installed the sprinklers on Tuesday. The heads that are shown are only temporary, until they finish the "bucket test". Then, much smaller brass heads will be installed.