5719 Project
Track the progress of our Sun Room Addition
Sunday, September 26, 2010
Countertops are in!!!
The blue highlights in the granite give it a little "pop".
Friday, September 24, 2010
Backsplash and Fireplace Tile
Thursday, September 23, 2010
BBQ Hood is in
Saturday, September 18, 2010
Cabinets are going in!
The cabinet bases are in, interior painting has started. The granite counter tops are being finished. TheBBQ hood venting is all fabricated and ready to be
installed.
Saturday, September 11, 2010
Flooring is being installed
The drywall is finished and the ceramic tile flooring is being installed. The outside stucco is also done. Not much longer before it's done.